You are here:Home » Quality Control

2 fiber extrusion facilities.

Total production capacity:

200 tons per day

Facility 1 capacity:

50 tons per day

Facility 2 capacity:

150 tons per day

Raw materials:

100% polyester chips

100% polyamide chips

Polyester chips are transported by air compressor via a network of tubes from the first level to the fifth level.

Polyamide chips are transported directly to the fifth level via freight elevator.

On the fifth level, the chips are separated into different containers for cleaning and drying.

01Clean chips

Any water and dust on the surface of the chips are removed and the chips are cleaned thoroughly through this process.

02Remove static electricity

Oil is then added to the now clean and dry polyester and polyamide chips.

03Heat and melt chips

The polyester and polyamide chips are melted and mixed together.

Every ten days the main components are cleaned and conditioned for optimum performance.

Polyester melting point: 250 degrees Celsius Polyamide melting point : 220 degrees Celsius

04Produce complex fiber from single filament

A single complex fiber can include 36, 72, 144 or 288 single filaments.

05

Packing complex fibers by rolls (10kg/roll, 15kg/roll, 20kg/roll)

06Testing fiber quality

Test and analyze the density, strength, color, extension, oil content, twist, and cutting by microscope.

Polyester Physics Standard
No. Item unit Excellent AA Good A AcceptableB Second Quality C
1 Fiber Density different dtex ±3.0 ±5.0 ±8
2 Breaking Strength cn/dtex ≧2.2 ≧2.0 ≧1.8
3 Strength % ≦4.5 ≦7.0 ≦10.0
4 Breaking extension % M±6.0 M±10.0 M±12.0
5 Extension % ≦4.5 ≦8.0 ≦10.0
6 Color difference % ≦1.2 ≦1.5 ≦2.2

Fibers -------Finished Yarn:

Draw- Twist Facility:

Fibers to finished yarn for weaving

We have 8 draw-twist machines. Capacity:

25 tons per day.

Heating ----Drawing-----Adding twist-----Forming ---- Spooling

Spools: small spools are combined into larger spools that fit the weaving machines. 265 small spools create one large spool (90kg).

Each machine will use 24 or 32 large spools.

Weaving Facility: 18 weaving machines

Capacity: 14 ton per day

6 advanced German machines

Capacity: 1200kg per day

12 standard machines

Capacity: 600kg per day

Each roll has its own unique ID, including the following information: production date, machine number, serial number, specifications, yarn number and roll weight.

Identify each colored cloth by its own unique ID .

Raw cloth and colored cloth are inspected for the following

Raw Cloth: width / yarn quality / weight per square meter

Colored Cloth: color consistency / width / cleanliness / weight, etc.

Cutting

Automatic Layering Machines

260,000pcs per day

Sewing

Automatic Sewing Machines

Packing

2 Needle Detectors .